Major Project Produces Fun Facts

Major Project Produces Fun Facts
10.28.2020

Leave it to the Baker Group cast of characters to notice the fun side of a major project – as well as successfully taking care of all the serious aspects.

Working with Mortenson, general contractor, building a central utility plant (CUP) for Vermeer Corporation, Gary Seymour, Senior Mechanical Engineer at Baker Group, pumped out these fun facts. Building Information Modeling (BIM) was the key tool employed in the project, beginning with the November 2019 presentation to Mortenson through shop fabrication and field installation. Actual work on the 10-month Design-Build project began last February.  From day one, the virtual model was used as the team brought together multiple facets of this tightly timed project to enable all involved to see, understand, manage and build the CUP, from concept into reality. Expecting the Best is easier when you can see it!     

Have a look.

Fun Facts

Qty

Units

·         number of field welds on large overhead piping mains

0  

ea

·         how long it took to get large piping put in place overhead

2

days

·         miles of electrical conduit inside building

3

miles

·         Baker Group shop pre-fabrication of large piping

5

weeks

·         miles of electrical wire inside building

10

miles

·         Megawatts of power to drive the CUP at full capacity

10

Megawatts

·         average crew size in Baker Group fabrication shop involved in project

12

people

·         average crew size on site for project

14

people

·         approximate number of semi deliveries from Baker Group Shop to Jobsite

22

ea

·         largest diameter of buried piping sending water to buildings

24

inches

·         largest diameter piping used in CUP

36

inches

·         design chilled water temperature leaving the CUP

40

degrees F

·         shop schedule worked during pre-fabrication

58

hrs/wk

·         design water temperature entering the cooling towers from the chillers

95

degrees F

·         longest overhead pipe craned in place, empty weight 25,000 lbs

114

ft long

·         number of shop welds on large overhead piping

883

ea

·         lineal feet of piping inside CUP

1,507

lineal ft

·         total motor horsepower required to pump water around

2,250

Hp

·         CUP cooling capacity would provide air conditioning for approximately

2,400

average houses

·         number of face masks used due to COVID-19

4,000

ea

·         tons of cooling provided for campus-day 1

4,400

tons

About Baker Group

Founded in 1963 and with more than 700 employees across Iowa, Baker Group is the Midwest’s premier full-service specialty contractor providing mechanical, sheet metal, electrical, compressed air, building automation, process automation, security systems, fire alarm systems, parking/revenue controls and 24/7/365 service. For more information, call 855.262.4000 or visit https://www.thebakergroup.com/.

News

Best of Des Moines 2023

Best of Business Record Award

Baker Group was recognized by readers of the Des Moines Business Record for best Mechanical Contractor, Electrical Contractor, Security Company and Best Company to Work For in 2023.

Top Workplaces

Best of Business Record Award

For a seventh consecutive year, Baker Group was recognized by the Des Moines Register as one of the Top Workplaces in the state.